Each R requires 2 of component S and 1 of part T. The lead time for assembly of R is 3 days. The lead time for the manufacture of S is 5 days. The lead time for the manufacture of T is 10 days. The cumulative lead time for R is __________ days.


A) 6
B) 9
C) 13
D) 17
E) cannot be determined

F) D) and E)
G) A) and B)

Correct Answer

verifed

verified

What are time fences? Why are they used?

Correct Answer

verifed

verified

Time fences allow a segment of...

View Answer

Which of the following regarding enterprise resource planning (ERP) is true?


A) It involves an ongoing process for implementation.
B) It can incorporate improved, reengineered "best processes."
C) It has a software database that is off-the-shelf coding.
D) ERP systems usually include MRP, financial and human resource information.
E) All of the above are true.

F) None of the above
G) A) and B)

Correct Answer

verifed

verified

Describe finite capacity scheduling. How is it more realistic than MRP?

Correct Answer

verifed

verified

FCS provides the precise scheduling need...

View Answer

MRP is generally practiced on items with dependent demand.

A) True
B) False

Correct Answer

verifed

verified

The quantity required of a dependent demand item is computed from the demand for the final products in which the item is used.

A) True
B) False

Correct Answer

verifed

verified

Effective use of MRP and other dependent demand models does not require which of the following?


A) master production schedule
B) bill of materials
C) inventory availability
D) lead times
E) cost of individual components

F) A) and E)
G) A) and D)

Correct Answer

verifed

verified

Wheeled Coach uses __________ as the catalyst for low inventory, high quality, tight schedules, and accurate records.

Correct Answer

verifed

verified

material r...

View Answer

The __________ is the input to material requirements planning which lists the assemblies, subassemblies, parts, and raw materials needed to produce one unit of finished product.


A) bill of material
B) master production schedule
C) inventory records
D) assembly time chart
E) net requirements chart

F) B) and E)
G) C) and D)

Correct Answer

verifed

verified

While ERP may provide a strategic advantage over competitors, it is so complex that many companies cannot adjust to it.

A) True
B) False

Correct Answer

verifed

verified

MRP is an excellent tool for scheduling products with variable lead times.

A) True
B) False

Correct Answer

verifed

verified

One of the tools that is particularly useful in reducing the system nervousness in the MRP system is (are)


A) modular bills
B) time phasing
C) time fences
D) lot sizing
E) closed loop system

F) B) and C)
G) C) and D)

Correct Answer

verifed

verified

Consider the following bill of material. Forty units of Product A are needed. Assuming no on-hand inventory, and no scheduled receipts, explode the bill of material. Consider the following bill of material. Forty units of Product A are needed. Assuming no on-hand inventory, and no scheduled receipts, explode the bill of material.

Correct Answer

verifed

verified

Item A: 40 units; Item B: 40 * 2 = 80 un...

View Answer

A company is trying to implement MRP but is having trouble determining which order sizing method will minimize costs. Setup cost is $200 and holding cost is $2/period. If each period is 1 week, gross requirements are 270 units per 10 weeks, and there are 6 planned order releases for every 10 weeks, calculate the cost for lot-for-lot compared to EOQ for an entire year. Assume that EOQ and lot-for-lot are computed as though the usage will occur continually throughout the year.

Correct Answer

verifed

verified

EOQ: D(yearly)=27/week*52 weeks = 1404 u...

View Answer

Four A washers, Five B washers, Two C bolts, and a D bolt are required to make one Grill parts kit. If 100 grill part kits are needed how many more washers will be consumed than bolts?

Correct Answer

verifed

verified

Using MRP explosion gives A:40...

View Answer

Distortion in MRP systems can be minimized when safety stock is held at the


A) purchased component or raw material level
B) work-in-process level
C) finished goods level
D) A and B
E) A and C

F) None of the above
G) C) and E)

Correct Answer

verifed

verified

Firms may discover that, rather than adapting ERP to the way they do business, they have to adapt the way they do business to accommodate the ERP software.

A) True
B) False

Correct Answer

verifed

verified

If a load report (resource requirements profile) shows a work center scheduled beyond capacity


A) the company must add capacity by enlarging the facility
B) the company must add capacity by such tactics as overtime and subcontracting
C) the work center's load may be smoothed by such tactics as operations splitting or lot splitting
D) the aggregate plan must be revised
E) the Wagner-Whitin algorithm should be used to rebalance the load

F) B) and E)
G) A) and B)

Correct Answer

verifed

verified

Which of the following is False concerning enterprise resource planning (ERP) ?


A) It attempts to automate and integrate the majority of business processes.
B) It shares common data and practices across the enterprise.
C) It is inexpensive to implement.
D) It provides and accesses information in a real-time environment.
E) All of the above are true.

F) A) and D)
G) B) and C)

Correct Answer

verifed

verified

The MPS calls for 50 units of Product A and 60 of B. There are currently 35 of Product B on hand. Each A requires 2 of Part C; each B requires 5 of C. There are 160 units of C available. a. Calculate the net requirements for B. b. Calculate the gross requirements for C. c. Calculate the net requirements for C.

Correct Answer

verifed

verified

(a) 60 - 35 = 25; (b...

View Answer